Paddington Station
 

The Paddington Integrated Project (PIP) is a joint venture between Crossrail (CRL), Network Rail (NR), London Underground (LUL) and Transport for London (TFL). This document focuses on the London Underground, Final Fit Out (FFO) aspect of the works. The works involved Final Fit Out (FFO) of the back of house areas to the new Paddington Hammersmith & City Line Station (H&C), which is served by LUL’s H&C Line. The works were undertaken within the newly constructed H&C Line station building and the refurbished H&C line island platform. The new station structure required fitting out of 4 main areas, Basement Level, Concourse Area, Mezzanine Level, and the existing platform.

 

The works were required at Paddington H&C Line Station, which is served by London Underground Limited’s Hammersmith & City Line, providing a link to Paddington Network Rail Station and London Underground Paddington main station served by Bakerloo, District and Circle Lines.

 

The FFO works delivery was broken down into six packages as listed below and included in the Specific Works Information. LUL was appointed in the role of Principal Contractor under Construction Design and Management Regulations 2007 (“CDM”) and URS were appointed designers for the FFO phase. · Premises (Incl. Minor Civils & Demolition) · Mechanical (incl. Public Health) · Electrical · Fire · Communications · Lifts (Awarded to KONE)

1/2

 

Client

LUL, TfL, NR, CRL

Location

Paddington Station

Contract Start and Completion

June - 

Discipline

Capital Works / Civils


Scope of works

Cleshar where contracted to assist on the on-going servicing of site compounds including Site Waste Management and welfare facilities for the Contractor. There were five other trade contractors working on the FFO. We were contracted to complete the following: ·

  • Erection of hoardings

  • Site Vehicle and pedestrian access/egress

  • Surveys and dilapidation reports

  • Provision of security guards 24/7.

  • Installation of Site welfare facilities, temporary power/ lighting/ Water supplies

  • Demolition of the structure housing the 2 existing CERs (LUL SID 1/952 & 1/731) at the western end of the platform 15/16 and Switch room E12 at the east end of the platforms.

  • Excavation in existing platform and the installation of a mass concrete base for the installation of new stair 05. ·

  • Replacement of the platform slabs below the demolished structures ·

  • Replacement of Paving to Platform 15 & 16.

  • Construction of the new emergency stairs (Stair 05), from the concourse level to platform 15 – 16 ·

  • Construction of new internal walls for all the new rooms on the concourse and mezzanine levels. ·

  • Construction of new walls separating the back of house area and the hall, including glazing ·

  • Removal of the over track crossing (OTX) ·

  • Painting and decoration